Does Elkhorn asbestos pose health threat?
1996 report identified six
contaminated areas
By GREGORY FOLEY
Express Staff Writer
As Sun Valley city officials Tuesday
prepared to issue a final permit for the demolition of the Elkhorn Resort, some
Elkhorn Village property owners remained concerned that asbestos at the site
could pose a public health threat.
Some Elkhorn residents during the permit
application process expressed wariness about asbestos in the buildings scheduled
to be razed in coming weeks by resort owner CG-Elkhorn LLC.
Other residents have expressed a
broadening concern in recent weeks, as the extensive demolition project drew
closer.
"I wish I wasn’t in town (during this),"
said Dorris Gathrid, an Elkhorn Village resident.
Asbestos inhalation has been determined to
cause various health disorders, including a rare form of cancer called malignant
mesothelioma.
For most, the concern about the demolition
project stems directly from the building’s history. Johns-Manville Corp.,
formerly one of the world’s leading asbestos manufacturers, was a partner in the
development of the 132-unit Elkhorn Hotel in the early 1970s.
However, David Hennessy, demolition
project manager for CG-Elkhorn, said the early 1970s brought a gradual phase-out
of the use of asbestos in building projects nationwide.
Hennessy said asbestos was used in the
construction of some of the buildings at Elkhorn Resort, but not in large
amounts. "The amount of asbestos in buildings of this size is very, very minor,"
he said.
Hennessy explained that an extensive
survey of so-called "Asbestos Containing Materials" was conducted at the resort
property in 1996. He said the project identified several locations in which
asbestos was found.
The June 1996 study by Boise-based
Materials Testing and Inspection, Inc. listed six specific areas where asbestos
was found among 105,000 square feet of buildings at the Elkhorn Resort site.
Former resort owner Milton G. Kuolt II commissioned the report.
The report identified asbestos in sheet
vinyl in the resort’s golf-course maintenance building, the former Jesse’s
Kitchen restaurant, the Plaza Grill bar, and a kitchenette in the resort‘s
conference building. It also cited findings of asbestos in the mastic (adhesive)
beneath the floor tiles in the Jesse’s site and the former Elkhorn General Store
on the village plaza.
Three of the six sites were identified
with a "high" hazard ranking of six points on a seven-point scale, while the
remaining areas were designated with a hazard ranking of three points.
Numerous other sites suspected to possibly
contain asbestos were determined to have none, the report notes.
An executive summary of the report states:
"Prior to renovation or demolition of this building, measures must be taken to
notify the US EPA."
Hennessy said CG-Elkhorn last year had the
1996 asbestos survey updated, and last April hired a private contractor to
remove the dangerous asbestos-containing materials.
The work conducted by Twin Falls-based
Metcalf Abatement focused on the materials identified in Jesses’s Kitchen.
Hennessy noted that a large section of
floor tile in the general store was not required to be removed because the
materials contained less than 1-percent asbestos. In addition, he said the
asbestos in the golf-course maintenance building has not been treated because
that building will not be razed.
"All that paperwork was filed with the
EPA," he said.
E.C. Cullen, asbestos coordinator for
Boise-based Industrial Hygiene Resources, a contractor for the federal
Environmental Protection Agency, said procedures for the project have been
followed so far.
Cullen said he will keep an eye on the
demolition project to ensure that proper procedures are followed, but will not
monitor it on a daily basis. He said he "might do an unannounced inspection" of
the site, and will be available to respond to "a legitimate complaint."
Cullen explained that not all identified
asbestos is required to be removed from the buildings before they are
demolished. He said only asbestos that is "friable," meaning it can become
airborne, must be removed under federally mandated regulations and brought to an
approved landfill.
The city generally approved the demolition
project last month. However, work at the site has been limited so far because a
final permit was delayed while CG-Elkhorn and the city negotiated a "financial
security agreement" to cover any project-related costs imposed on the public.
Dan Pincetich, Sun Valley city
administrator, said Tuesday that the matter was close to being resolved. "We
expect it to happen today," he said Tuesday.