Detour placed at
East Fork intersection
Timber Way
intersection may close
By PETER
BOLTZ
Express Staff Writer
A temporary
change in the location of East Fork Road’s intersection with Highway 75,
completed Monday night, was the first of several possible changes to an
ongoing road construction project.
The detour
moves the intersection to the south, about 150 feet north of the Greenhorn
fire station.
The detour
was in response to public concerns about the intersection’s safety. Tom
Logan, project inspector for the Idaho Transportation Department, said the
detour will allow motorists coming out of East Fork to see farther and
more clearly before entering the highway.
Before
construction is completed, the intersection will be moved back to its
original spot, where a traffic light will be installed.
Another
possible change would be the permanent closure of the intersection of
Timber Way, a quarter mile north of the East Fork intersection. The Wood
River Regional Transportation Committee voted to recommend the closure
during a meeting Thursday in the old Blaine County courthouse.
The
committee advises the county commissioners about transportation issues.
Its voting members include one commissioner and representatives from
Blaine County cities.
The closure
will not be effected unless it is approved by the commissioners and the
ITD. If the change is included, residents of the Timber Way neighborhood
would reach the highway through the Golden Eagle II subdivision, across
from East Fork Road.
The
committee also approved Ketchum’s resolution to limit the number of
single-occupancy vehicles coming into town by restricting parking there.
The resolution now goes to the commission, which will decide how to
incorporate it into a countywide transportation plan.
Ketchum
City Administrator Jim Jaquet, present for the vote, called it a
"watershed event."
Jaquet said
all the entities in the county should be working together to provide
disincentives for single-occupancy vehicles and incentives for carpooling
and public transportation.
Another
possible change was presented by ITD environmental manager Chuck Carnohan.
He said the department could shorten the "transition" of the
left turn lane on the north side of the intersection of Highway 75 and
East Fork Road.
The highway
at that point will have two southbound lanes and two northbound lanes. ITD’s
plan has been to taper the width of those five lanes to meet the existing
three-lane configuration over a distance of about a mile.
However,
Carnohan said, that could be done in the space of one-quarter mile. He
said an example of such a taper exists at the intersection with Elkhorn
Road.
But, he
stressed, the shortening is something that "could be done, not what
we propose to do."
The current
plan to taper the highway over the distance of a mile will remain in place
pending the committee’s receipt of more information.
Diana
Atkins, of the consulting engineering firm Parsons Brinckerhoff, told the
committee that her firm will create a traffic simulation model to estimate
future travel patterns. Atkins said she expects to have a prototype ready
by Oct. 15.
That
information will become part of the project’s environmental review
process. An Environmental Impact Statement, under the National
Environmental Policy Act, will help determine what a new Highway 75 from
Timmerman Hill to Ketchum will look like.
ITD
Director Dwight M. Bower has acknowledged that work underway between
Alturas Drive and Timber Way will be subject to change if it is in
conflict with the findings of the EIS. In an April 5 letter to the county
commissioners, he wrote that the project, except for the Greenhorn bridge,
"will not be deemed a pre-existing federal commitment."
Atkins said
she expects a draft EIS to be completed in two years.