Ketchum and Sun Valley hold special
election
Voters asked Tuesday to
fund sewage plant upgrade
"If we don’t do this now, the cost will
go up not only with interest rates but also with the costs themselves of the
plant."
— ED SIMON, Ketchum mayor
By GREG MOORE
Express Staff Writer
Ketchum and Sun Valley voters will be
asked in a special election Tuesday, Feb. 3, to allow their cities to proceed
with a $7.4 million upgrade of their jointly owned wastewater treatment plant—a
project that officials say the cities have no choice but to undertake.
Mike Herrera, supervisor of the
wastewater treatment plant that serves Ketchum and Sun Valley, makes an
adjustment to the plant’s chlorine disinfection system. The city of Ketchum and
the Sun Valley Water and Sewer District—which jointly own the plant—are
proposing to replace the system with a new ultraviolet light disinfection
system. Express photo by Willy Cook
Ballots can be cast at only one location
in each of the two cites. Polls at Ketchum City Hall and at Sun Valley City Hall
will open at 8 a.m. and close at 8 p.m.
Registered voters in both cities can
submit absentee ballots at their respective city hall until 5 p.m. Monday, Feb.
2.
In presentations to both city councils on
Tuesday, Jan. 20, representatives from Boise-based Pharmer Engineering said the
existing plant has almost reached capacity, is too old to buy spare parts for
and by 2006 will no longer meet state and federal water quality standards.
Violations of those standards could result in fines of up to $10,000 per day.
"These are things we have to do, both from
a wastewater treatment standpoint and to protect the Big Wood River," said Sun
Valley Water and Sewer District General Manager Jack Brown.
The upgrade would include two new
buildings and the replacement of much of the facility’s wastewater treatment
equipment. If all goes as planned, construction will begin next spring and be
completed by 2006.
The main components of the proposed plant
upgrades include:
-
A $1.5 million disinfection system that uses ultraviolet light to bombard
bacteria and other micro-organisms, destroying their ability to reproduce.
-
Filters—costing $2.5 million—that would remove enough suspended solids and
phosphorus to meet more stringent limits established by the Big Wood River
Watershed Management Plan. The plan was developed by the Idaho Department of
Environmental Quality and approved by the U.S. Environmental Protection
Agency.
-
New aeration basins—costing $1.8 million—that will double current aeration
capacity. The current aeration system is operating at 70 percent capacity but
cannot function adequately if one of two aeration basins is out of service.
-
A $1.3 million electrical and control system that includes a new 700 kilowatt
generator.
One benefit of the upgraded plant is that
it would no longer use chemicals to treat sewage. The current plant uses 840
pounds of chlorine each month as part of its treatment process, and 500 pounds
of sulfur dioxide to dechlorinate the treated water. The gases can pose a hazard
during their transportation and handling.
Steve Hansen, Ketchum utilities manager,
said the replacement of chemical disinfection treatments with UV light
treatments would effectively eliminate a potential threat of chemical traces
being discharged into the Big Wood River.
"The benefit to the environment, to the
river, would be a huge plus," Hansen said.
Steve Hansen, Ketchum utilities
manager, and Mike Herrera, Ketchum wastewater plant supervisor, inspect the
site of a proposed new wastewater disinfection system that will use ultraviolet
light to destroy bacteria and other single-cell organisms. The improvement is
part of a planned $7.4 million upgrade that requires approval of Ketchum and Sun
Valley voters. Express photo by Willy Cook
Because the plant is owned jointly by the
city of Ketchum and the Sun Valley Water and Sewer District, each agency would
be obligated to pay half the $7.44 million cost. The upgrade would be funded by
either a government loan or a bond issue.
Ketchum City Administrator Ron LeBlanc
said that once the cities have received voter approval to incur debt, they will
have the option of choosing one or both funding methods, depending on interest
rates.
LeBlanc said that with a current interest
rate of only 3 percent, the loan program looks more favorable. The program was
created under the federal Clean Air Act, and involves federal money distributed
by the state of Idaho.
If by construction time a bond issue
appears most advantageous, Ketchum would issue revenue bonds, repaid by
increases in monthly sewer fees and in impact fees for new construction.
The Sun Valley district has determined it
would issue general obligation bonds. General obligation bonds are a type of
municipal bond for which principal and interest are secured by the credit of the
bond issuer and supported by the issuer’s taxing power.
Due to the difference in the types of
bonds the cities would issue, voter approval will need to come from only a
majority of Ketchum voters, but from two-thirds of Sun Valley voters.
Brown said money to repay the debt would
initially be collected from Sun Valley residents by an increase in property
taxes, probably amounting to $23 per $100,000 valuation.
Ketchum Mayor Ed Simon said sewer bills
for single-family homes in Ketchum would probably rise from the current $13 to
$15. He pointed out that even with the increase, Ketchum residents will be
paying about $10 less than do Hailey residents and $5 less than Bellevue
residents.
Sun Valley residents now pay $16.50 in
sewer bills.
"If we don’t do this now, the cost will go
up not only with interest rates but also with the costs themselves of the
plant," Simon said.
The new plant would be designed to meet
the cities’ needs for the next 20 years. Greg Misbach, water quality engineer
with the Idaho Department of Environmental Quality, said state and federal water
quality standards for treated effluent should not change appreciably during that
time.
(Express staff writer Gregory Foley
contributed to this report.)