Elkhorn Resort
finding new life
Much of hotel, restaurants recycled,
reused
By GREGORY FOLEY
Express Staff Writer
Despite being reduced to rubble in recent
weeks, Elkhorn Resort is finding new life among a series of other projects in
Idaho and beyond.
During the demolition of the 132-unit
hotel in March and April, several tons of the resort’s materials were salvaged
for reuse or recycling.
Work crews last winter salvaged an
abundant amount of materials from Elkhorn Resort, including parts of the
roof of the River Rock Steak House building on the north side of Elkhorn
Village, top photo. On Tuesday, workers for demolition contractor Twin Falls
Crane Service put the finishing touches on their project by adding fill and soil
to the site of the former Elkhorn Hotel, bottom photo. Express photos by
Willy Cook
Jim Thorpe, owner of Twin Falls Crane
Service, the company that conducted the project, said that although some 6,000
tons of building debris was trucked to a regional landfill, a significant amount
of the Elkhorn Hotel, River Rock Steak House and Treat Haus buildings was
salvaged.
Thorpe kicked off a sale of a portion of
the salvaged materials on Saturday in southern Twin Falls at the old Norco
window factory.
The salvage sale is scheduled to continue
daily through mid-May, but could terminate sooner if all of the materials are
sold.
"It’s going really well," he said. "We’re
about half sold (out) in three days."
Thorpe said numerous buyers at the sale
over the weekend traveled to Twin Falls from various cities in Blaine County,
southern Idaho and Nevada.
Items offered in the sale include windows,
furniture, carpeting, dishes and doors from the defunct resort’s buildings.
Overall, approximately 3,000 tons of wood
debris and an equal amount of concrete debris were unable to be recycled, Thorpe
noted.
However, most other materials were
separated for reuse. All told, more than 10 tons of copper, steel and aluminum
were recycled. Among the items kept for reuse were 291 tons of wood beams, 6,210
tons of steel beams, 4,600 square feet of plywood, 110 doors, six tons of river
rock and 25,000 paver pieces. Also salvaged were the buildings’ elevators, floor
tiles and rafters.
Thorpe said the demolition essentially
went as planned. "The only glitch in the whole job was the rain during the last
two or three weeks."
Of 65 trees slated for removal as part of
the project, only one was taken out, he added.
Thorpe said crews this week would install
5,500 tons of gravel backfill at the site. After the fill is in place, crews
will add approximately 1,700 tons of topsoil from the Wood River High School
construction site in Hailey, he noted.
Once the site is filled in and graded, a
separate contractor will begin landscape work on the property, Thorpe said.
The owner of the property, CG-Elkhorn, is
preparing an application to redevelop the property with a mix of residences and
commercial spaces.