INEEL
cleanup
gathers momentum
Citizens Advisory
Board
gives basic approval
By GREG
MOORE
Express Staff Writer
An
accelerated U.S. Department of Energy timetable for cleaning up buried
nuclear waste at the Idaho National Engineering and Environmental
Laboratory met with basic approval from the site’s Citizens Advisory
Board during a meeting in Sun Valley last week.
The plan
may finally be putting into motion a decades-old effort to remove or
stabilize chemical and radioactive contaminants--byproducts from the
nation’s Cold War weapons production programs--stored at the federal
research facility east of Arco.
Kathleen
Hain, INEEL team leader for environmental restoration, told the
15-member board at the Sun Valley Inn on Wednesday that excavation on
the notorious Pit 9 will begin by the end of September 2003. That would
be six months ahead of the schedule set out in an agreement made in
April between the DOE and the state of Idaho.
"They’re
moving along very aggressively on this," said advisory board member
David Kipping, a resident of Hailey. "I think there is a great
emphasis on doing the project as quickly as possible."
The
initial work will be a demonstration project on a 20-by-20-foot section
of the one-acre pit. Retrieval of plutonium-contaminated waste will
provide detailed information on what’s there and how to best go about
cleaning up the entire Radioactive Waste Management Complex, a 97-acre
spread of 20 pits and 58 narrower trenches.
Hain said
Pit 9 was chosen for the demonstration work solely because of its ease
of access. A previous cleanup effort was begun there in 1995, but
abandoned three years later after a subcontractor of Lockheed Martin,
which was managing INEEL at the time, became bogged down in technical
and financial problems.
Bechtel
BWXT Idaho took over responsibility for the Pit 9 project in 1999 when
it became the management and operating contractor for the INEEL.
The waste
complex contains drums of mostly transuranic waste--that is, radioactive
materials contaminated with manmade elements heavier than
uranium--dumped there during the 1950s and 1960s. Most was generated by
nuclear weapons production at the Rocky Flats DOE site west of Denver.
The wastes are leaking hazardous chemicals, and perhaps radioactive
material, into the Snake River Plain Aquifer.
During
the 1950s and most of the 1960s, DOE placed barrels in rows in the pits,
and kept records of what was in each. In 1969, however, the barrels were
dumped randomly, then crushed and covered with dirt.
"Those
drums are not quite intact," Hain said. "That’s where we
started to have problems with retrieval."
Hain told
the board that the operation will be the first time buried transuranic
waste has been retrieved anywhere. She said the results will disclose
the accuracy of shipping records and whether the techniques used are
effective with the type of waste and soils at the site.
"The
very first thing that will come out of this demonstration is that you
can safely retrieve transuranic waste," she said.
The DOE
began construction of the structure used to enclose the operation on
July 30, four months ahead of schedule.
Hain said
a mockup of the containment structure will be done by mid December, at
which time workers can begin training to excavate the drums and handle
the materials inside them.
The
workers will operate a backhoe from outside the structure, which will
use negative air pressure to contain airborne contaminants stirred up
during excavation. The waste will be placed on carts that will transport
it within the containment structure to gloveboxes, where workers will
separate the materials. Excavation is planned to take less than three
months, and be done by December of next year.
Once
separated, the materials will be repackaged in barrels and stored above
ground pending treatment by the Advanced Mixed Waste Treatment Project,
expected to be on line by next March. The facility will put the waste
into a form suitable for shipment to and permanent disposal at the Waste
Isolation Pilot Plant in New Mexico.
The
demonstration project at Pit 9 will give the DOE information to draft a
plan on dealing with the remaining buried waste. Under its agreement
with the state, such a plan must be completed by 2007. Hain said public
comments will be officially sought before a plan is finalized.
In 1995,
the DOE and the state of Idaho signed an agreement requiring all
transuranic waste at INEEL to be placed in permanent disposal by 2018.
However, a dispute over whether the agreement requires all the buried
waste to be removed, or whether some of it can be treated "in situ"
and left in place, is before the U.S. District Court in Boise. The DOE
estimates that removal would cost about 10 times that of "in situ"
treatment, which involves surrounding the waste with an impermeable
material such as grout or melted glass. Either way is expensive--the
agency estimates retrieval costs to run about $1 billion per acre, and
in-situ treatment to be about $700 million per acre.
Transuranic
waste received at INEEL since 1970 has been placed in temporary storage
above ground, rather than buried. Some of that waste, already in a
condition for disposal, is now being shipped to WIPP. Under the 1995
agreement, 3,100 cubic meters, out of the 65,000 cubic meters of waste
stored above ground, must be shipped out of the state by Dec. 31. The
DOE has said it expects to meet that deadline.