Hailey highway
project on schedule
ITD: Work should
be done by Aug. 20
By GREGORY
FOLEY
Express Staff Writer
Crews
from Bellevue-based Valley Paving have started work to resurface a
1.3-mile stretch of Main Street in Hailey, and are on schedule to finish
the project by Tuesday, Aug. 20, an Idaho Transportation Department
official has announced.
Crews
from Valley Paving of Bellevue on Monday used a massive milling
machine to remove the asphalt surface of Main Street in Hailey. Workers
are scheduled to resurface the road with new asphalt starting next
Monday.
Tom
Logan, ITD project manager, said Monday that crews through Thursday are
scheduled to tear up the old road surface from Airport Way near the town
post office to just south of McKercher Boulevard near Albertsons’
supermarket.
State
contractors on Friday will start paving a "test strip" along
the busy stretch of road to determine what mix and density of asphalt
will best suit the project, Logan said.
Crews on
Monday will start resurfacing the section of Main Street with new
asphalt, and will then replace the manholes and paint new street
markings Aug. 19 and 20, Logan said.
Work will
start on the south end of the city and move north, Logan noted.
Measures
will be taken to try to reduce the project’s impact on traffic flow
along the busy stretch, which through town is designated as both Main
Street and Highway 75.
At least
one lane in each direction will remain open to traffic at all times
during the project, and two lanes will be kept open for commuter traffic—heading
north in the morning and south in the afternoon—at most times, Logan
explained.
No
official detour will be established for motorists to get around the
construction area, Logan said.
"However,
motorists would be advised to follow alternate routes," he said.
Traffic
in downtown Hailey could also be slowed next week by temporary changes
to the traffic signal at the intersection of Main Street and Croy
Street. Logan said the traffic lights at the intersection starting
Monday will be operated temporarily on timed sequences instead of
programmed light triggers attached to traffic sensors.
Valley
Paving also is scheduled to resurface a section of Highway 75 through
downtown Ketchum, starting after Labor Day, and Sun Valley Road from
Ketchum to the National Forest boundary just east of Trail Creek Cabin
in October.
Logan
added that the state’s ongoing project to widen Highway 75 from
Alturas Drive to Timber Way is on schedule for completion by Sept. 1.
He said
Idaho Sand & Gravel crews will start paving the roughly two-mile
stretch starting around Aug. 19.
"We’re
getting down to the point where once the paving is completed, we’re
just going to be doing cleanup and landscaping," Logan said.
The new
section of the highway should be open to motorists on Labor Day weekend,
Logan said.